Construction update: Our new office and shop are coming along!
Construction update: Our new office and shop are coming along! Roof trusses and purlins in the office are done, and roof steel is complete for the shop. Paving on the south side was postponed to Monday due to rain. The goal is to finish all south side concrete paving by next week. Window installation in the office is set for Monday. In the coming weeks, gas line and meter installation, along with phone/internet trenching, are planned.